There were tradies at work inside the house when I visited
this afternoon (Saturday). This is the first time I have encountered them
working on the house over the weekend. The brickwork is now complete. However,
the fibre cement infills above the windows on the south side are yet to be
done.
Saturday, 27 February 2016
Saturday, 20 February 2016
Bricks and Insulation
The bricklaying has now started and is due to be completed
mid next week. Our bricks look very similar to those being used for the house behind ours. Great minds. Completion of the bricklaying will bring us up to lockup and another progress payment
will be due. The insulation has now been installed and the plastering is due begin
next week.
North Side of House |
South Side |
Heating Ducts |
Walk In Robe and Ensuite |
Lounge |
Garage |
Kitchen and Dining |
Rear Passageway |
Saturday, 13 February 2016
Solid Progress
The roof tiles have been laid. The sliding doors and some windows have
been installed. The breather membrane has also been wrapped around most of the
frame. The “rough in” by the electrician and plumber is complete. I have been
advised that the bricklayer is due to commence this coming week.
Monday, 8 February 2016
Frame Complete