Fenced off and Finished ?

I arrived at Solsbury today to find access was fenced off. It seemed to me that the development work was either compete or close to completion. However, I was unable to scrutinise things closely due to the lack of access. I could see that the roads were sealed and the street signs were in place.

A couple of weeks ago, we received a letter from the real estate agent that listed each subdivided lot and the corresponding street number assigned to it. The letter also stated that the developer had advised that settlement was now expected in mid to late August.



Around the same time we supplied a copy of the developer’s compaction report to Orbit to assist with the determination of the foundation requirements for our house. We’ve now been informed that the engineering analysis has been undertaken and slab design is complete. We are expecting to receive a building contract with fixed site costs this week.