Wednesday 15 June 2016

Final Inspection

We have received the final invoice from Orbit but are still awaiting the Occupancy Permit. The final inspection is scheduled for this Friday. The Independent Inspector has already been through the house. He has identified 23 defects. Most of them relatively minor and a few more significant. The pictures below were taken by the inspector yesterday.

View from the Road

Front Entrance

Bedroom 1


Ensuite Shower
Ensuite Basin and Toilet

Ensuite Mirror

Laundry

Kitchen

Family Room

Family Room - Another Angle

Sunday 5 June 2016

In A Holding Pattern

Our trusty Balwyn 196 appears to be stuck in a holding pattern waiting to land. The Expected Time of Arrival is still uncertain. 

By peering through the front window into the main bedroom at the front I was able to confirm that the carpet has been laid. However I also noted that the en suite basin was lying on the floor of the main bedroom. I'm fairly certain that this position is not consistent with the plumbing or the plans. A further visit from the plumber will be required. As I understand the regulations, it is not possible to obtain an occupany certificate until all the plumbing is complete, including the fitting of the basins. Other items still outstanding are barrier doors and the infills above the doors.


Streetscape - A couple of weeks ago

Streetscape Today - Neighbours appear to be
Entertaining (I hope)


We appear to have gained some Waffle Pods.
I wonder how much I would get for them on ebay.

Infills above Doors still needed.


A new Slab - 2 Doors Down.

Barrier Doors Still Needed.

Drainage - Not so Good