Saturday 20 February 2016

Bricks and Insulation

The bricklaying has now started and is due to be completed mid next week. Our bricks look very similar to those being used for the house behind ours. Great minds. Completion of the bricklaying will bring us up to lockup and another progress payment will be due. The insulation has now been installed and the plastering is due begin next week.          