Dropped by the block on my way to Cranbourne this
morning. Good progress has been made in
the last few days with the meter box installed, the set out complete and the
drains in place. I think there’s only 1 week of construction work to go before
the building industry take their month long Christmas break.
With the exception of possible showers on Tuesday the
forecast for the rest of next week is for fine weather. However, there is quite
a lot of work required to complete the slab by Friday. The pile of dirt must be
removed, the concrete formwork must be set-up and the waffle pods put in place.
Although there was no sign of any waffle pods at the site this morning, I
remain optimistic. If the slab was completed by Friday the concrete would have
a full month to cure before work on the frame commences. On the down-side the
first progress payment of 10% would be due.